Faster Permitting of Energy Projects: The EU Is Preparing a Major Reform of Permitting Procedures

The permitting process has long been the biggest obstacle to the development of energy infrastructure in the European Union. While building an electricity grid can take approximately ten years, more than half of that time may be spent obtaining permits. Permitting for renewable energy projects can take up to nine years in some Member States, while energy storage projects may take between one and seven years.

On 10 December 2025, the European Commission presented a proposal for a directive to accelerate permitting for renewable energy projects, electricity grids and related energy infrastructure.

The proposal forms part of the European Grids Package. It aims to support the faster development and modernisation of European energy networks. On 2 July 2026, the European Parliament’s Committee on Industry, Research and Energy (ITRE) supported the proposal by 57 votes to 3, with 8 abstentions. It also requested a mandate to negotiate with the Council of the EU, with negotiations expected to commence under the Irish Presidency.

For developers, energy companies, industrial businesses and investors, this is a development worth monitoring already today, even though the legislative process has not yet been concluded.

What the proposal entails

The proposed directive amends three existing EU legal acts. These are the Renewable Energy Directive (2018/2001), the Electricity Market Directive (2019/944) and the directive governing the natural gas and hydrogen markets (2024/1788). It is therefore not an entirely new standalone legislative act. Rather, the proposal introduces targeted amendments to three key directives that together form the regulatory framework for permitting energy projects in the EU. Its objective is to shorten permitting deadlines, harmonise permitting procedures for major and cross-border projects, and reduce the administrative burden for both investors and public authorities.

The package also includes a so-called EU-wide coordination regime (referred to in expert discussions as the “28th regime”) for selected major energy infrastructure projects. Its aim is to establish a more centralised framework for coordinating permitting processes at EU level and to reduce administrative fragmentation in projects of cross-border significance.

One point of contact, one process

The proposed directive aims to introduce a more integrated permitting model. Under this model, several relevant areas are to be coordinated through a single competent authority or a joint permitting procedure. This is also linked to the obligation for Member States to establish a single digital portal. The portal is intended to facilitate the various permitting steps for renewable energy projects, energy storage and electricity grids. It is also to be connected to environmental and geological data. The same obligation to establish a digital platform is to apply to the gas and hydrogen sectors.

For applicants, this means in practice that they will have to submit a more comprehensive package of technical, environmental and project documentation at the application stage. The aim is to limit requests for additional documents during the procedure and thereby shorten its overall duration.

Shorter deadlines and “silence means consent”

In certain cases, the proposal also provides for a so-called silent approval mechanism. If the competent authority fails to respond within the prescribed time limit at a particular stage of the permitting process, Member States could treat its failure to act as consent. ITRE also proposes that procedures concerning connection to the electricity grid should not take longer than three months. For selected projects, silent approval would apply if this deadline is exceeded. For the actual connection to the electricity grid, the proposal establishes deadlines of six to nine months, depending on the location and technology.

The capacity thresholds triggering the obligation to obtain a permit are also being increased—from 100 kW to 200 kW for small solar installations, energy storage and charging stations. Charging stations with an installed capacity of up to 1 MW located on artificial structures (e.g. buildings) should not require a permit at all. A particularly short deadline is also proposed for heat pumps with a capacity of up to 50 MW—one month (three months for ground-source heat pumps), again subject to silent approval.

Overriding public interest and simplified environmental assessment

The proposal strengthens the presumption of overriding public interest for renewable energy and electricity grid projects. The aim is to support their prioritised permitting. ITRE also proposes limiting the ability of Member States to narrow this presumption or introduce exemptions from it in their national legislation. The only exception would be the necessary protection of legally protected cultural heritage.

The proposal introduces a temporary exemption from environmental impact assessment for the refurbishment and modernisation of existing electricity grids. Environmental assessment would focus primarily on new infrastructure elements. The proposal also simplifies the repowering of wind projects where no new land is required. At the same time, it clarifies the rules for assessing alternative solutions and compensatory measures under EU environmental law.

Sharing benefits with local communities

The proposal also strengthens the mechanism for sharing the economic benefits of a project with local residents and communities directly affected by it. ITRE proposes lowering the threshold triggering the obligation to share project benefits from 10 MW to 7 MW. It also expressly excludes community and citizen renewable energy projects from this obligation. Particular emphasis is placed on ensuring that vulnerable households receive an adequate share of the benefits. The amendments also include the establishment of an independent mediator to facilitate dialogue between the investor and the public.

What this means for businesses today

The legislative process has not yet been concluded. The Council of the EU adopted its negotiating position on the proposal at the end of June 2026, and negotiations on the final wording of the directive will follow once the European Parliament has adopted its position. The proposal provides for a two-year deadline for transposition into national law. The final wording may therefore still change in certain details.

Nevertheless, the direction of future European and, subsequently, Slovak legislation is already clear. It is moving towards significantly faster and more predictable permitting procedures for renewable energy projects, electricity grids, energy storage, charging infrastructure and, to some extent, the gas and hydrogen sectors.

Developers and investors in energy projects, industrial companies with their own energy plans, as well as public sector entities, should therefore monitor the development of the proposal already at this stage. New capacity thresholds, shorter deadlines and benefit-sharing obligations may affect both projects currently in preparation and future projects. It is therefore advisable to take them into account already during the planning phase.

Given the links with existing Slovak permitting procedures (construction proceedings, EIA and grid connection), the changes will also require amendments to national legislation. At the same time, they will create an opportunity for affected entities to safeguard their interests already during the transposition process.

The LEGATE team has been closely monitoring legislative developments in energy law at both European and national level for a long time. We provide legal advice to energy companies, industrial groups and public sector entities in permitting procedures and investments in energy infrastructure. If you are interested in consulting on the impact of the proposed directive on your project, please contact us at legate.sk.